This Deliverable presents a preliminary techno-economic assessment of the DelHyVEHR bunkering station.

The scope of the study focuses on a preliminary estimation of the investment required for the installation of the station, based on initial design of the system and its main equipment components.

Overall, the results indicate that the cryogenic storage is the equipment with the higher contribution of the overall cost to the station, especially for high capacities. The optimisation of the hydrogen supply chain could contribute to the reduction of these costs. For smaller capacity stations, cost-reduction strategies targeting other equipments components could increase the overall profitability of the station, especially in the near future with low hydrogen-powered vehicles in the market to be refuelled. 

Download Deliverable 6.1 here